| CLIENTS BRIEF
To maximise the use of space to provide Private Flats.
Extensive survey work had to be undertaken prior to being able
to assess the number of flats we could actually fit within the curtilage
of the existing building. Fundamental to our role was to examine
how many flats we could incorporate into the design against the
cost of bringing the building back into use. In other words, the
cost of the development compared to the projected sales or rental
value.
Planning permission was successfully sought and obtained from the
Local Planning Authority.
Preliminary work had to be carried out to mitigate any surprises
synonymous with conversion/refurbishment works. The following surveys
were undertaken i.e. condition survey, structural survey, damp-proof
survey, video drainage survey, electrical and mechanical survey.
Hard costs could now be established against the results of the
survey and this information would be incorporated both within the
tender documentation and the specification/detailed drawings and
documents that would eventually be submitted for Building Regulations
Approval and tender purposes.
All drawings and documents to Building Regulations were successfully
approved and we were commissioned to project manage the works and
oversee all aspects of Health and Safety under Construction Design
and Management Regulations (CDM).
|